Story Points commitment completion
eazyBI for Jira

On this page:

Overview

Track the story points commitment completion by sprints in the selected project – story points committed, added, completed of committed, completed of added, and committed completion %.

How to build it

To build this report, start with the table view and select the Sprint dimension in Rows, select the "Sprint" level from the "By status" hierarchy to see the report information at the sprint level.

In the Measures dimension, select measures: 

Filter the report rows by the measure Last closed sprints by boards with the condition "=<10". Remove the measure "Last closed sprints by boards" from the report view, the filter is still active and will filter the last ten closed sprints in the report. 

In Pages, select the dimension "Project" for filtering. When the sample report is created in eazyBI, eazyBI automatically selects the first project with report measures for filtering. Additionally, add "Issue type" in Pages and select "All Issue Types by type" from the "By type" hierarchy to filter issues by Standard issue types. Also, add a "Sprint" dimension in "Pages" and filter all Closed sprints. Select the option "Hide empty rows" to hide rows without data.

Then, switch to the Bar tab and select Vertical and Stacked in the toolbox options. Change colors for measures. To measure "Sprint Story Points committed completion %," change the type to a line, and use a separate axis (for example, 1) to show the percentage on a separate scale. Add a description to the report.